Along with the coming of the information age, the excellent IT skills are the primary criterion for selecting talent of enterprises. Nokia Certification gives an IT a credential that is recognized in the IT industry. It can act as a passport to a well-rewarded job, smooth the path to promotion or higher earnings. Here, Nokia certification PDM_2002001060 exam (CPM) is a very important exam to help you get better progress and to test your IT skills.
How to successfully pass Nokia PDM_2002001060 certification exam? Don't worry. With DumpKiller, you will sail through your Nokia PDM_2002001060 exam.
DumpKiller is a website that provides the candidates with the excellent IT certification exam materials. The Nokia certification training PDM_2002001060 bootcamp on DumpKiller are on the basis for the real exam and are edited by our experienced IT experts. These dumps have a 99.9% of hit rate. So, we're sure it absolutely can help you pass Nokia PDM_2002001060 exam and get Nokia certificate and you don't need to spend much time and energy on preparing for PDM_2002001060 exam.
DumpKiller provides you with the most comprehensive and latest Nokia exam materials which contain important knowledge point. And you just need to spend 20-30 hours to study these PDM_2002001060 exam questions and answers from our PDM_2002001060 dumps.
One year free update for all our customers. If you purchase DumpKiller Nokia PDM_2002001060 practice test materials, as long as PDM_2002001060 questions updates, DumpKiller will immediately send the latest PDM_2002001060 questions and answers to your mailbox, which guarantees that you can get the latest PDM_2002001060 materials at any time. If you fail in the exam, please send the scanning copy of your PDM_2002001060 examination report card provided by the Test Center to the Email address on our website. After confirming, we will give you FULL REFUND of your purchasing fees. We absolutely guarantee you interests.
Before you decide to buy Nokia PDM_2002001060 exam dumps on DumpKiller, you can download our free demo. In this way, you can know the reliability of DumpKiller.
No matter what level you are, when you prepare for Nokia PDM_2002001060 exam, we're sure DumpKiller is your best choice.
Don't hesitate. Come on and visit DumpKiller.com to know more information. Let us help you pass PDM_2002001060 exam.
Easy and convenient way to buy: Just two steps to complete your purchase, we will send the PDM_2002001060 braindump to your mailbox quickly, you only need to download e-mail attachments to get your products.
Nokia CPM Sample Questions:
1. Which of the following statements is not in line with reporting rules? New non-planned Risk identified with a significant value:
A) does not change as sold cost estimate (ASCE) and cost baseline (CBL).
B) changes the estimate at completion (EAC) value of non conformance costs.
C) does not change the estimate at completion (EAC) value of the risk contingency.
D) changes the cost baseline (CBL) value of the risk contingency.
2. Who should contribute to the development of the project plan?
A) Project manager.
B) Network planning.
C) The entire project team including the project manager.
D) Senior management.
3. The risk contingency reserve is identified in which process?
A) Estimate activity resources.
B) Estimate activity duration.
C) Determine cost baseline.
D) Estimate costs.
4. Under what circumstances should the costs associated with the execution of the quality management plan be included in the project cost baseline?
A) Quality management costs must always be considered in the project plan as the benefits outweigh the costs in terms of less rework, higher productivity and higher stakeholder satisfaction.
B) Quality Management costs should not be part of the project cost baseline as it is the obligation of the subcontractor to perform according to the contract.
C) Costs associated to quality management should be considered only in very complex projects when the risk of quality issues cannot be fully mitigated.
D) Quality Management costs should not be part of the project cost baseline but be entirely transferred to subcontractors that under-perform.
5. The project cost management plan is created as a part of the:
A) estimate costs process.
B) determine budget process.
C) control costs process.
D) project management plan process.
Solutions:
Question # 1 Answer: D | Question # 2 Answer: C | Question # 3 Answer: C | Question # 4 Answer: A | Question # 5 Answer: D |