Along with the coming of the information age, the excellent IT skills are the primary criterion for selecting talent of enterprises. Microsoft Certification gives an IT a credential that is recognized in the IT industry. It can act as a passport to a well-rewarded job, smooth the path to promotion or higher earnings. Here, Microsoft certification 70-178 exam (Microsoft Project 2010, Managing Projects) is a very important exam to help you get better progress and to test your IT skills.
How to successfully pass Microsoft 70-178 certification exam? Don't worry. With DumpKiller, you will sail through your Microsoft 70-178 exam.
DumpKiller is a website that provides the candidates with the excellent IT certification exam materials. The Microsoft certification training 70-178 bootcamp on DumpKiller are on the basis for the real exam and are edited by our experienced IT experts. These dumps have a 99.9% of hit rate. So, we're sure it absolutely can help you pass Microsoft 70-178 exam and get Microsoft certificate and you don't need to spend much time and energy on preparing for 70-178 exam.
DumpKiller provides you with the most comprehensive and latest Microsoft exam materials which contain important knowledge point. And you just need to spend 20-30 hours to study these 70-178 exam questions and answers from our 70-178 dumps.
One year free update for all our customers. If you purchase DumpKiller Microsoft 70-178 practice test materials, as long as 70-178 questions updates, DumpKiller will immediately send the latest 70-178 questions and answers to your mailbox, which guarantees that you can get the latest 70-178 materials at any time. If you fail in the exam, please send the scanning copy of your 70-178 examination report card provided by the Test Center to the Email address on our website. After confirming, we will give you FULL REFUND of your purchasing fees. We absolutely guarantee you interests.
Before you decide to buy Microsoft 70-178 exam dumps on DumpKiller, you can download our free demo. In this way, you can know the reliability of DumpKiller.
No matter what level you are, when you prepare for Microsoft 70-178 exam, we're sure DumpKiller is your best choice.
Don't hesitate. Come on and visit DumpKiller.com to know more information. Let us help you pass 70-178 exam.
Easy and convenient way to buy: Just two steps to complete your purchase, we will send the 70-178 braindump to your mailbox quickly, you only need to download e-mail attachments to get your products.
Microsoft Project 2010, Managing Projects Sample Questions:
1. Standard working hours are eight hours a day from Monday through Friday. You create a task of fixed units
and set the duration to 2 days. You assign the task to John at 100 percent. John wants to work only 50
percent on the task. You change John's assignment units to 50 percent for the task.
Which set of values describes the specified task?
A) Duration shows 4 days; Work shows 8 hours
B) Duration shows 2 days; Work shows 0 hours
C) Duration shows 2 days; Work shows 16 hours
D) Duration shows 4 days; Work shows 16 hours
E) Duration shows 2 days; Work shows 8 hours
2. You need to ensure that when you add new tasks, the project schedule doesn't set a start date and end date. What should you do?
A) On the Advanced tab of the Project options, clear the Automatically add new resources and tasks check box.
B) Select Task from the main ribbon menu. Highlight the task that you want to change and select Manually Schedule.
C) Click New Tasks and change the option to Auto Scheduled.
D) On the Schedule tab of the Project options, change the New tasks created option to Manually Scheduled.
E) On the Display tab of the Project options, clear the Edits to start and finish dates check box.
3. You create a new Gantt Chart view. You need to copy the view to a different project. What should you do?
A) Use the Links Between Projects tool.
B) Use the Organizer tool.
C) Use the Compare Projects feature.
D) Use the Save Views feature.
4. In the default Gantt Chart view of your Project Professional 2010 project, you need to display the following information:
-Tasks that are not started.
-Tasks in progress.
-Tasks that have finished.
-Total remaining effort for each group of tasks.
What should you do on the View tab?
A) Select Group by Complete and Incomplete Tasks, and then add the Work field to the table.
B) Select Group by Active v. Inactive, and then add the Remaining Work field to the table.
C) Select Group by Complete and Incomplete Tasks, and then add the Remaining Work field to the table.
D) Select Group by Active v. Inactive, and then add the Work field to the table.
5. You manage several projects. Each project has shared resources and work distribution. You need to ensure that you can adjust the workload for specific resources used across multiple project schedules. What should you do?
A) Open a blank project and select Insert Subproject for each project schedule. Then, use the Level Resource function for selected resources.
B) Open the shared Resource Pool for each project schedule. Then, use the Level Resources function.
C) Enable the Load Summary Resource Assignments option. Then, select the Level Resource function on each project.
D) Open the individual schedules and use the Visual Reports option. Then, use the Resource Usage view to manually modify resource Work.
Solutions:
Question # 1 Answer: D | Question # 2 Answer: D | Question # 3 Answer: B | Question # 4 Answer: C | Question # 5 Answer: A |