Along with the coming of the information age, the excellent IT skills are the primary criterion for selecting talent of enterprises. Microsoft Certification gives an IT a credential that is recognized in the IT industry. It can act as a passport to a well-rewarded job, smooth the path to promotion or higher earnings. Here, Microsoft certification 070-178 exam (Microsoft Project 2010, Managing Projects) is a very important exam to help you get better progress and to test your IT skills.
How to successfully pass Microsoft 070-178 certification exam? Don't worry. With DumpKiller, you will sail through your Microsoft 070-178 exam.
DumpKiller is a website that provides the candidates with the excellent IT certification exam materials. The Microsoft certification training 070-178 bootcamp on DumpKiller are on the basis for the real exam and are edited by our experienced IT experts. These dumps have a 99.9% of hit rate. So, we're sure it absolutely can help you pass Microsoft 070-178 exam and get Microsoft certificate and you don't need to spend much time and energy on preparing for 070-178 exam.
DumpKiller provides you with the most comprehensive and latest Microsoft exam materials which contain important knowledge point. And you just need to spend 20-30 hours to study these 070-178 exam questions and answers from our 070-178 dumps.
One year free update for all our customers. If you purchase DumpKiller Microsoft 070-178 practice test materials, as long as 070-178 questions updates, DumpKiller will immediately send the latest 070-178 questions and answers to your mailbox, which guarantees that you can get the latest 070-178 materials at any time. If you fail in the exam, please send the scanning copy of your 070-178 examination report card provided by the Test Center to the Email address on our website. After confirming, we will give you FULL REFUND of your purchasing fees. We absolutely guarantee you interests.
Before you decide to buy Microsoft 070-178 exam dumps on DumpKiller, you can download our free demo. In this way, you can know the reliability of DumpKiller.
No matter what level you are, when you prepare for Microsoft 070-178 exam, we're sure DumpKiller is your best choice.
Don't hesitate. Come on and visit DumpKiller.com to know more information. Let us help you pass 070-178 exam.
Easy and convenient way to buy: Just two steps to complete your purchase, we will send the 070-178 braindump to your mailbox quickly, you only need to download e-mail attachments to get your products.
Microsoft Project 2010, Managing Projects Sample Questions:
1. You have team members who work on one of the following shifts: Monday through Friday: 8 hours a day. Tuesday through Saturday: 10 hours a day. Sunday through Wednesday: 12 hours a day. You need to ensure that your project plan accommodates the different shifts. What should you do?
A) Create a base calendar for each shift.
B) Create shift resource departments.
C) Create three tasks, one for each shift.
D) Change the maximum units for each resource.
2. The project you manage has only part-time resources. The part-time resources work four hours a day from Wednesday through Saturday. You need to create a new calendar and set the calendar as the default for your project. Which two actions should you perform? (Each correct answer presents part of the solution. Choose two.)
A) Change the Calendar type in the Project Options dialog box.
B) Set the calendar type to part-time for all tasks.
C) On the Project tab, Select Change Working Time, and then click Create New Calendar.
D) Select the part-time calendar from the Project Information window.
E) Select the part-time calendar from the Change Working Time window.
3. You need to view only the task name, start and finish dates, percentage of work completed, and a Gantt chart. What should you do?
A) Create a custom table and a custom view.
B) Create a custom filter and a custom table.
C) Create a custom table and a custom group.
D) Create a custom filter and a custom view.
4. You manage several projects. Each project has shared resources and work distribution. You need to ensure that you can adjust the workload for specific resources used across multiple project schedules. What should you do?
A) Open a blank project and select Insert Subproject for each project schedule. Then, use the Level Resource function for selected resources.
B) Open the shared Resource Pool for each project schedule. Then, use the Level Resources function.
C) Enable the Load Summary Resource Assignments option. Then, select the Level Resource function on each project.
D) Open the individual schedules and use the Visual Reports option. Then, use the Resource Usage view to manually modify resource Work.
5. Your project has a part-time resource who works 4 hours a day from Monday through Thursday. You need to ensure that your project plan accommodates the part-time resource. What should you do?
A) Change the working time for the resource.
B) Change the maximum units for the resource.
C) Assign the resource only to tasks that are scheduled on the working days.
D) Update the base project calendar.
Solutions:
Question # 1 Answer: A | Question # 2 Answer: C,D | Question # 3 Answer: A | Question # 4 Answer: A | Question # 5 Answer: A |